March 11 – Resolute Brewery Update (Centennial, CO)

(…chug, chug, putter, psssssssttttt…) Well, Resolute’s time machine is out of commission…After a look under the hood it appears we are only outputting 1.20 Gigawatts of power.  Until we can find that last 0.01 Gigawatt, this week’s Resolute Brewery Update will have to be in the present time, not a month in advance.

Resolute Time Machine

Furniture

As announced a few weeks ago, Resolute has teamed with & Collaborative to design and construct our taproom furniture.  As of this week, each of the pieces of furniture have been designed and a contract has been signed.  In the coming weeks, Resolute will be announcing a rare opportunity for members of the community sponsor individual pieces of furniture, leaving their namesake forever engraved in the Resolute taproom (plus a whole lot of free pre-opening SWAG).  Stay tuned to social media and this blog for details, as the finite sponsorship opportunities will sell out fast!

[simple_slider arrows=”always” nav=”dots” transition=”slide” auto_rotation=”1″ fullscreen=”1″]
[simple_slide img=”https://resolutebrewingco.com/wp-content/uploads/2016/03/XSheetBarStool.jpg” alt=”Resolute Bar Stool”]
[simple_slide img=”https://resolutebrewingco.com/wp-content/uploads/2016/03/Sheet-Metal-Chair-Midcentury-Modern.jpg” alt=”Resolute Chair”]
[simple_slide img=”https://resolutebrewingco.com/wp-content/uploads/2016/03/AngledSqLeg-4-Top.jpg” alt=”Resolute Table”]
[simple_slide img=”https://resolutebrewingco.com/wp-content/uploads/2016/03/RectangularBarTable.jpg” alt=”Resolute High-Top”]
[simple_slide img=”https://resolutebrewingco.com/wp-content/uploads/2016/03/20BarTable.jpg” alt=”Resolute Window Bar”]
[simple_slide img=”https://resolutebrewingco.com/wp-content/uploads/2016/03/Wood-Circle-Coffee-Table.jpg” alt=”Resolute Coffee Table”]
[/simple_slider]

TTB Update

Resolute is in a holding pattern…the TTB front has been neither good nor bad.  At this point in time, we have no reason to believe anything but the average processing times to be expected.

Construction Update

With permits fully submitted, our amazingly superb architect, H+L Architecture, is nearly complete and ready to hand the torch off to our general contractor. Construction of our taproom will be a visible sign of progress toward our summer opening.  Until now, much of our team’s work has revolved around licensing, planning, and finances.  When Howell begins demolition and construction, we will do our best to document daily progress with photos and commentary.  As of now, the final budget and contract should be signed this week.  Subcontractors will be awarded their work, and procurement can begin this week or next.

SWAG Update

Stickers are starting to find their way onto community sticker boards across the city.  There has even been a sighting on a mini-van.  In addition to stickers, business cards and shirts have been picked up.  Stay tuned on social media for pictures!  Hats, coasters, taproom glasses, and other SWAG are still yet to come.

[simple_slider arrows=”always” nav=”none” transition=”slide” auto_rotation=”1″ fullscreen=”0″]
[simple_slide img=”https://resolutebrewingco.com/wp-content/uploads/2016/03/ResoluteStickerDoor-1.jpg” alt=”Resolute Sticker Door”]
[simple_slide img=”https://resolutebrewingco.com/wp-content/uploads/2016/03/ResoluteStickerMiniVan-1.jpg” alt=”Resolute Sticker Mini-Van”]
[/simple_slider]

 

Thanks for tuning in!  Don’t forget to follow us on Facebook, Twitter or Instagram for mid-week updates.  Until then, as my kiddos would say, TTFN!